PennDOT roadwork scheduled to get underway this week includes a concrete repair project on Route 22 in Burrell Township. The work is scheduled Monday through Thursday in the westbound lanes between the Route 119 interchange and Snyder Lane, with a single-lane restriction in place. It’s part of a $3.1 million project that includes additional locations in Indiana County.
The Anthony Run Road bridge replacement project begins Monday in Armstrong Township. Anthony Run Road will be closed through August 23rd between the Route 422/Anthony Run Road intersection and Curry Run Road. The detour will use 422 and Parkwood Road. The $1.17 million bridge replacement is scheduled to be completed by the end of August.